The project team is working to create a new Web site for the company. The Web site is the _____.
a. deliverable
b. requirement
c. stakeholder
d. milestone

Respuesta :

exceloffcity
exceloffcity exceloffcity
  • 02-11-2018

B. The requirement :/

Answer Link

Otras preguntas

Help please algebra !!
Joe's gas tank is 3/10 full. After he buys 14 gallons of gas, it is 4/5 full. How many gallons can Joe's tank hold?
What are some general considerations one should keep in mind when selecting protec- tive clothing for use in the shop environment?
The amygdala is the brain region that is most often called into action under situations of
Predict what would happen to the egg white if a raw egg were placed in vinegar
Contrast the atmosphere with the biosphere
How much information is enough for an accountant to comply with the full disclosure principle?
What statements about the atomic structure were validated by his cathode ray experiments?
find the distance between the pair of points. ( square root 5, square root 2) and -3 square root 5, 5 square root 2)
three-fourth of the student body attended a pep rally. if there were 1230 students at the pep rally, how many students are there in all